ITS to continue network upgrade in selected academic buildings throughout July
Information Technology Services began an upgrade to 无码专区's entire network last November and will continue with the upgrade throughout July.
As part of this upgrade, ITS will visit individual academic and administrative buildings on the Starkville campus to install new network equipment.听
Careful consideration has been taken on scheduling building upgrade dates to minimize the impact on听academic classes and administrative work.听听
听听
Please be aware of the following on the day a building is scheduled to be听upgraded as the听building will be without network connectivity (wired and wireless) all day.听听
- Phones will be unavailable during the upgrade.听
- Instructors should be prepared to deliver course material from another听location if network access is required.听听
- ITS-supported lecterns will not be functional during the day of the scheduled upgrade.
- Academic buildings with classrooms scheduled to be upgraded during the month of听July are as follows:听
- Friday, July 2听
- Magruder Hall听
- Patterson Engineering Building
- Friday, July 9
- McComas Hall
- Friday, July 16
- Dorman Hall
- Dorman Hall Greenhouse
- Friday, July 23
- Howell Building
- Landscape Architecture Administration
- Landscape Architecture Freehand Studio
- Landscape Architecture Seminar Studio
- Friday, July 30
- Industrial Education Building
- Friday, July 2听
If there are extenuating circumstances that would exclude one of the above buildings from being updated on the specified date and/or time, please immediately notify the ITS Service Desk at 662-325-0631 or听servicedesk@msstate.edu.
听听
Thank you for your cooperation and understanding during this critical network听upgrade.听听听